Dibba Bulk Handling Terminal – Package 4 (Port Buildings

Year: 2018-on going
Client: Port of Fujairah
Location: Fujairah – UAE
Description: Port of Fujairah (PoF) is planning the development of a 15 MTPA (maximum 19 MTPA) Bulk aggregate handling terminal in Phase 1, at the existing Dibba Port in Dibba, Emirate of Fujairah. The proposed materials to be transported and exported includes Limestone, Gabbro and Clinker. FNCT is bidding for the execution of Package 4 – Buildings (Port) Contract.
MUC Engineering: Contractor’s Consultant for tender support, basis of design, detailed design and Preparation of NOC documentation and obtaining required NOCs.

Port of Fujairah – Service Harbour Phase 2 – Marine Works and Buildings

Year: 2013-2014
Client: Port of Fujairah
Location: Fujairah – UAE
Description: Construction of a new quay wall for the extension of Port of Fujairah Oil Terminal 2, Phase 2, Berths 8 and 9. The total length of the quay wall is 890m and has a retaining height of 23.6m. The structure is a combi wall with driven Ø1420mm tubular piles. As anchoring system MV piles were used with a total length of 50m. The structure has been installed using marine equipment.
MUC Engineering: Client’s Consultant for detailed design and Project Management and Supervision.

Port of Fujairah – Service Harbour Phase 1

Year: 2016-2018
Client: Port of Fujairah
Location: Fujairah – UAE
Description: Development of a new Service Harbour as extension of Port of Fujairah. MUC Engineering has developed a masterplan for the harbor as well as the design of breakwaters, land reclamation quay walls.
MUC Engineering: Client’s Consultant for detailed design and Project Management and Supervision.

Port of Fujairah Tanker Berths 3A and 3B

Year: 2016-2017
Client: Port of Fujairah
Location: Fujairah – UAE
Description: Construction of 2 new berths for Bunker tankers were realized for tankers up to a length of 120m. The project includes the realization of all mechanical, electrical and instrumentation topside facilities related to tie of the new berths to the existing manifold.
MUC Engineering: Client’s Consultant for detailed design and Project Management and Supervision.

Port of Fujairah OT2

Year: 2009-2015
Client: Port of Fujairah
Location: Fujairah – UAE
Description: Construction of a new Marine Oil Terminal as extension of the Port of Fujairah Oil Terminal 1. New Berths 4, 5, 6, 7, 8 and 9 were realized with a total length of wall of 2340m and with a retaining height up to 23.6m. Additionally 5 million m3 dredging has been carried out to bring the basin to -18m depths as well as the construction of 1500m long breakwater.
MUC Engineering: Client’s Consultant for detailed design and Project Management and Supervision.

Engineering building – Port of Fujairah

Year: 2016

Location: Port Of Fujairah, Fujairah, UAE

The existing engineering building at the Port of Fujairah, definitely needed a proper facelift. Normally such building would be demolished to be replaced with a new one. Since renovation contributes to the sustainability concept, re-use of the existing structures and adding square meters  in the form of an additional floor was an ideal solution. Within a tight budget, we have been constructed to scrutinize the existing building and to devise a concept for this.

The existing building consists of two parts; one part is constructed in 1985 and the other part in 1989. The idea is to extend this building with additional square meters and by adding a new floor on top of the existing and old structure, we had the idea to combine all structures into a new building.

PoF Engineering Building - Before
Engineering building in Port of Fujairah before reconstruction

The gray collar which can be seen, melts the structures together into one building. The projecting portion on the corner emphasizes an orientation point, it is manager’s office.

MUC was responsible for the architectural design, structural detailing and tendering.