Port of Fujairah, OT2 Phase 2

Year: 2013-2014
Client: Port of Fujairah
Location: Fujairah – UAE
Description: Construction of a new quay wall for the extension of Port of Fujairah Oil Terminal 2, Phase 2, Berths 8 and 9. The total length of the quay wall is 890m and has a retaining height of 23.6m. The structure is a combi wall with driven Ø1420mm tubular piles. As anchoring system MV piles were used with a total length of 50m. The structure has been installed using marine equipment.
MUC Engineering: Client’s Consultant for detailed design and Project Management and Supervision.

Oil Terminal Expansion of the Port of Fujairah

Year: 2008 – 2009
Location: Fujairah – UAE
Client: Port of Fujairah
Description: Detailed design, guidance of the tender process and supervision over the construction works of Oil Terminal 2 phase 1 for the Port of Fujairah. The terminal comprises a new quay wall with a length of approx 1.7 for handling oil tankers up to 180,000 DWT, dredging of the entrance channel and harbour basin, reclamation and coastal protection works.

Port of Fujairah, OT2 Phase 1

Year: 2008-2010 (completed)
Client: Port of Fujairah
Location: Fujairah – UAE
Description: Realization of a quay wall for Port of Fujairah Oil Terminal 2, Phase 1 Including construction of 1.5km of combi wall with a retaining height of 22.8m, 800m of deep water breakwater and 5 million m3 of dredging and reclamation. After completion the facility is able to receive 4 tankers up to a size of 200,000 DWT or 8 handy size tankers.
MUC Engineering: Client’s Consultant for detailed design, Supervision and Project Management.